Aluepurkaus Made History
Aluepurkaus made history in Porvoo by completing its largest balcony demolition project to date. At As-Oy Porvoon Portti, a total of 414 concrete balconies were
1.
The first step on site is an interior inspection. Any cracks, damage, or other areas requiring special attention are documented.
2.
The balconies are closed off from the outside for safety reasons, and the doors are kept closed throughout the work.
3.
If the balconies have glass enclosures, they are removed before dismantling the structural components.
4.
The balconies are detached from the structure either by chipping (with jackhammers) or sawing — the method is chosen based on the construction. The elements are then lifted away.
5.
Finally, the open balcony line is carefully secured. At this point, our demolition work is complete, and the site is ready for the next phase of construction.
Whenever demolition takes place, we bring you the latest insights and stories from the demolition industry.
Aluepurkaus made history in Porvoo by completing its largest balcony demolition project to date. At As-Oy Porvoon Portti, a total of 414 concrete balconies were
A large leaking glass roof is being dismantled. Each glass pane weighs 150 kg, and the demolition conditions are challenging because there is a 30-meter
On April 5, 2023, ScanWorks Oy and Turun Aluekierrätys Oy agreed on a transaction in which the entire business operations of Helsingin Aluepurkaus Oy were
1.
Send us a request for quotation. We review the site and relevant documents (structural drawings, hazardous materials report, etc.), after which we prepare calculations and agree on the detailed scope of work.
2.
Following successful negotiations and signing the contract, we prepare the demolition work plan and safety plan.
3.
Includes a kickoff meeting, safety briefing, and staff induction.
4.
At this stage, we carry out the demolition, clean the site, and finally sort the materials for recycling.
5.
We deliver all necessary reports and load tickets to the client and handle invoicing. Once the invoice is settled, the project is officially complete.
Fill in the fields on the side and tell us about your demolition project — we respond quickly and tailor a proposal to meet your needs. Let’s carry out a safe and efficient demolition together!
You can also call us directly at: +35840 052 6885
NEED SOMETHING DEMOLISHED? Call Jukka!
Jukka Vesalainen
Phone: +358 400 526 885
jukka.vesalainen@aluepurkaus.fi